Goal
By the end of this guide, you will be able to correctly install an RS socket into a foundation and manage the installation or replacement of posts within the system.
Overview of the RS Retention System
Start hereThe RS Retention System is designed for the efficient installation and rapid replacement of various types of posts and street furniture. This guide covers the end-to-end process, from preparing the initial foundation to the final installation of a new post. Following these steps ensures a secure, vertical, and easily maintainable installation.
Site Preparation and Foundation
Before positioning the socket, the hole must be correctly prepared to ensure stability and drainage.
- Prepare a hole that is at least 75mm deeper than the overall height of the RS socket .
- If the required depth cannot be achieved, the unit can be shortened on-site .
- Compact at least 75mm of MOT type I granular material into the base of the hole for drainage.